Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long wouldRam take to complete the entire job alone?
(A) 6 days
(B) 8 days
(C) 10 days
(D) 11 days